Closure 1 - Directional bore for installation of electrical panel in alleyway

  • The sidewalk on the north side of Atlantic Ave between US1 and NE 7th Ave will be temporarily closed for that day (May 29th, 2018)
  • The alleyway on the south side of Atlantic Ave directly across the above referenced area (where Swell Crepes and Coffee is located) will be closed until June 1, 2018.

Closure 2 - Indefinite sidewalk closure on Ne 7th Ave for sheet pile installation

  • The sidewalk on the west side of NE 7th Ave will be closed indefinitely which is associated with the Atlantic Crossing projects developing stages.